| Milestone | Date |
| RFP Released to Bidders | Tuesday, January 20, 2026 |
| Final Date for Question Submittal | Friday, February 13, 2026 |
| Proposals Due | Friday, February 20, 2026 |
| Notification of Results | Friday, February 27, 2026 |
| Target Execution of Contract | Friday, March 13, 2026 |
Relevant questions and responses related to the Central Iowa Power Cooperative 2026 Request for Proposals for MISO Capacity will be posted on this page.
Yes, as long as they are relevant to the RFP.
Responses to questions will be provided as soon as practical. Response times will vary depending upon the complexity of the question.
At time CIPCO will only consider proposals through planning year 2029/2030, as outlined in the RFP.
CIPCO will not consider resources that do not have MISO Network Resource Interconnection Service (NRIS).